Contract Value
£1,200,000
Contract Period
Sep 2016 - Apr 2020
Sector
Public Transport

Project Overview

The contract was initially valued at £265k back in 2016 for 6 months works. As the contract has progressed, and scope massively increased, our team has proved invaluable to both Protec and Laing O'Rourke in the delivery of the installation. We were able to add value for the client with exceptional installation quality from benchmarks to finished installations.
view full case study (pdf)

Services Delivered

Providing Fire Detection installation services during the development of the Tottenham Court Road Crossrail Station, inclusive of:

  • Containment
  • Cable Installation and Management
  • Aspirating Installation
  • Detection Installation
  • Commissioning & Testing of all works

Challenges & Mitigations

Challenge

Deliver the high standard of electrical installations and cope with the increased scope of the project.

Mitigation

Throughout the project we collaborated with Protect to ensure a collaborative working relationship and environment is achieved across all staff and works.

Consequently, this has enabled us to:

• Meet all deadlines as per the programme (meeting all performance targets).

• Encourage a sharing environment for problems, commendations, and best practice.

• Delegate all works accordingly.

• Cross-report health and safety standards and compliance with legislation and rules.

Challenge

Mitigation

Challenge

Mitigation

Contact Details:

Highland Construction (Bridgend) Ltd

Call: 01656 720 330
Email: info@highland-services.com

Office Address:
1a Attlee Street,
Brynmenyn Industrial Estate,
Brynmenyn, Bridgend,
CF32 9TQ

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.