The 26-week programme was a key objective for the client and required our Project Team to overcome several potential challenges to deliver the works to schedule.
The works were undertaken in a live working environment, with the potential for disruption to NHS staff working within the building, and the general public. This required our experienced team to programme our works in line with these challenges, including allowing for out-of-hours working and controls to ensure that works adjacent to live areas were clearly signposted, segregated, and that the client was informed throughout. Measures to manage programme activities included:
Measures to manage programme activities included:
A key challenge during this project was related to associated building and civil engineering works, which were to be completed over winter. During that time, there was substantial rainfall, which prevented works from being completed and risked key delivery milestones from being achieved. Our ability to draw on competent locally available operatives allows us to increase labour to allow certain tasks to be completed in parallel, which would bring the delivery back in line with time requirements.
Through regular collaborative programme reviews with the client, we suggested the change to resource levels, which allowed the project milestones to be delivered to programme.
Using our risk management strategies, ongoing communication with the client, extensive experience of adapting our working practices to working in sensitive environments, we delivered the 26-week programme to budget and schedule.