Live Industrial Environment
The works were completed within an operational energy recovery facility, where industrial processes and critical infrastructure remained active throughout the project.
Works were delivered through a phased programme, with close coordination alongside site management and health and safety teams to maintain safe working practices and minimise disruption.
High-Risk Areas
The installation of an FD240-rated steel double door set required a high level of precision due to the enhanced fire-resistance requirements within the affected area.
Experienced installation teams followed tested specifications and BM TRADA-compliant methods to ensure the door set achieved the required level of performance.
Heavy-Duty Door Installations
The steel door sets required specialist handling and careful coordination during installation.
Mechanical handling requirements were planned in advance, with works completed by engineers experienced in industrial steel fire door systems.