Contract Value
Contract Period
Sector
Energy and Waste Management

Project Overview

Highland Services were appointed to complete fire door remediation works and specialist steel door installations at Viridor Energy’s Cardiff Energy Recovery Facility. The project formed part of a wider programme of fire safety improvements designed to enhance fire compartmentation and ensure access points across the facility met current compliance standards. Following a detailed fire door inspection report, the works were delivered across two phases and included a combination of new steel door installations and remedial upgrades to existing door sets.
view full case study (pdf)

Services Delivered

  • Installation of one FD240 steel double door set within a critical high-risk area
  • Installation of three additional steel double door sets
  • Installation of five steel single door sets
  • Remediation works to nine existing steel door sets
  • Fire stopping and sealing using approved fire mastic systems
  • Full sealing and finishing works to maintain fire integrity
  • Remedial works to address non-compliances identified within the fire door inspection report
  • Installation and quality-assurance processes completed in line with BM TRADA standards
  • Coordination with site management and health and safety teams throughout the programme

Challenges & Mitigations

Challenge

Live Industrial Environment

The works were completed within an operational energy recovery facility, where industrial processes and critical infrastructure remained active throughout the project.

Mitigation

Works were delivered through a phased programme, with close coordination alongside site management and health and safety teams to maintain safe working practices and minimise disruption.

Challenge

High-Risk Areas

The installation of an FD240-rated steel double door set required a high level of precision due to the enhanced fire-resistance requirements within the affected area.

Mitigation

Experienced installation teams followed tested specifications and BM TRADA-compliant methods to ensure the door set achieved the required level of performance.

Challenge

Heavy-Duty Door Installations
The steel door sets required specialist handling and careful coordination during installation.

Mitigation

Mechanical handling requirements were planned in advance, with works completed by engineers experienced in industrial steel fire door systems.

Contact Details:

Highland Construction (Bridgend) Ltd

Call: 01656 720 330
Email: info@highland-services.com

Office Address:
1a Attlee Street,
Brynmenyn Industrial Estate,
Brynmenyn, Bridgend,
CF32 9TQ

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.